KONONIVKA Solar PV Power Plant

«Kononivka» is a 2.7 MW solar photovoltaic power plant designed by AVENSTON in the 4th quarter of 2019 at the request of a Ukrainian investor. The project documentation of the stage “Project” was developed, which includes detailed technical solutions elaboration following the customer needs.

Ground-based solar power plant PV Plant Solar K is located in east part of Ukraine – Kononivka, Vyshchebulatetska settlement council, Lubenskyi district, Poltavska region, Ukraine. The power plant is putted into operation on 2020. “Solar K” LLC is a legal entity operating the power plant. It obtained the license for electricity generation on December 23, 2020 and permitted for the Feed-in-tariff in hryvnias equivalent of 10.97 eurocents starting from December 30, 2020.

 

Key project details:

  • Capacity – 2,7 MWp
  • Area – 4 ha
  • Solar panels – poly-Si (375 Вт)
  • Inverters – Huawei Sun 2000-60KTL and Huawei Sun 2000-50KTL
  • Location – Poltava region, Ukraine

Our services:

  • Consulting and assistance in business planning of the project
  • Analysis and selection of major technological solutions
  • Development of project documentation of the stage “Project”
  • Consulting on optimization of procurement and delivery of basic equipment and materials

AVENSTON provided assistance in business planning and client consulting, as well as analysis and selection of major technological solutions for the RES facility. Given the feasibility study, high-efficiency poly-Si modules and inverters of appropriate quality were selected. Also, the client was provided with consulting services to optimize the procurement and delivery of basic equipment and materials.

Many years of experience in the development and implementation of complex energy facilities allowed AVENSTON specialists to approach the Kononivka Solar project with a cost-effectiveness and efficiency point of view. We apply an individual approach to each customer and make all decisions based on the specifics of each project.

Solar power plants are one of the key competencies for companies belonging to the Avenston group. We provide any necessary services for solar energy projects, starting from the support of the development stage to maintenance of already built photovoltaic power plants or systems. All the main stages of the implementation of such projects are carried out by us independently or with the involvement of selected partners. In the second case, all key processes are managed and controlled by Avenston’s in-house project managers. Our portfolio includes a large number of designed and built industrial solar PV power plants, home solar power plants, as well as other projects in related areas.

 

More projects:

VILKHOVETS Solar BIPV Power Plant

Roof-mounted Vilkhovets BIPV solar power plant was built with the participation of companies from our group in the Kyiv region. Commissioning works and service support have been implemented by our company, too. Total power - 132 kWp.
Discover more

The project “Rehabilitation of street lighting in Ivanovka village”

The information on the project «Rehabilitation of street lighting in Ivanovka» using photovoltaic modules, which is being implemented by company of our group.
Discover more

SKADOVSK Solar power plant

Solar photovoltaic power station was built in Skadovsk district of Kherson region. The PV power plant covers an area of 20 hectares, with a total installed capacity of photovoltaic modules is 9,806 MW. This facility was built to produce clean electricity and its subsequent sale to the grid using the green tariff.
Discover more

COMPLEX Solar PV power plant

The Complex solar photovoltaic plant was built in Yampol district of Vinnitsa region. The solar power plant is located on a land plot of 2.5 hectares. The total capacity of power plants is 1742 kW.
Discover more