KONONIVKA Solar PV Power Plant

«Kononivka» is a 2.7 MW solar photovoltaic power plant designed by AVENSTON in the 4th quarter of 2019 at the request of a Ukrainian investor. The project documentation of the stage “Project” was developed, which includes detailed technical solutions elaboration following the customer needs.

Ground-based solar power plant PV Plant Solar K is located in east part of Ukraine – Kononivka, Vyshchebulatetska settlement council, Lubenskyi district, Poltavska region, Ukraine. The power plant is putted into operation on 2020. “Solar K” LLC is a legal entity operating the power plant. It obtained the license for electricity generation on December 23, 2020 and permitted for the Feed-in-tariff in hryvnias equivalent of 10.97 eurocents starting from December 30, 2020.

 

Key project details:

  • Capacity – 2,7 MWp
  • Area – 4 ha
  • Solar panels – poly-Si (375 Вт)
  • Inverters – Huawei Sun 2000-60KTL and Huawei Sun 2000-50KTL
  • Location – Poltava region, Ukraine

Our services:

  • Consulting and assistance in business planning of the project
  • Analysis and selection of major technological solutions
  • Development of project documentation of the stage “Project”
  • Consulting on optimization of procurement and delivery of basic equipment and materials

AVENSTON provided assistance in business planning and client consulting, as well as analysis and selection of major technological solutions for the RES facility. Given the feasibility study, high-efficiency poly-Si modules and inverters of appropriate quality were selected. Also, the client was provided with consulting services to optimize the procurement and delivery of basic equipment and materials.

Many years of experience in the development and implementation of complex energy facilities allowed AVENSTON specialists to approach the Kononivka Solar project with a cost-effectiveness and efficiency point of view. We apply an individual approach to each customer and make all decisions based on the specifics of each project.

Solar power plants are one of the key competencies for companies belonging to the Avenston group. We provide any necessary services for solar energy projects, starting from the support of the development stage to maintenance of already built photovoltaic power plants or systems. All the main stages of the implementation of such projects are carried out by us independently or with the involvement of selected partners. In the second case, all key processes are managed and controlled by Avenston’s in-house project managers. Our portfolio includes a large number of designed and built industrial solar PV power plants, home solar power plants, as well as other projects in related areas.

 

More projects:

Rooftop Solar PV Power Plant in Koziatyn

The solar photovoltaic plant was built in the Vinnytsia region on the roof of a manufacturing enterprise. The solar modules occupy an area of ​​2,562.6 square meters. The type of PV power plant: rooftop, on-grid, for self-consumption.
Discover more

RYKHTA Solar PV Power Plant

The ground based solar power station (photovoltaic station) "Rykhta" was built in the Khmelnytsky region. The power plant occupies an area of 5 hectares, and the total power of the installed solar panels (photoelectric modules) is 2,178 MW.
Discover more

RIVNIANSKA-2 Solar PV Power Plant

The solar power station (photovoltaic station) "Rivnianska-2" was built in the Kirovograd region. The power plant occupies an area of ha, and the total power of installed solar panels (photovoltaic modules) is 403 kW.
Discover more

GUTA-2 Solar PV Power Plant

The solar power plant (photoelectric plant) was built in the Uzhgorod district of the Transcarpathian region. The power plant covers an area of 5.73 hectares and the total capacity of installed solar panels (photovoltaic modules) is 3.48 MW.